Anlegg / Aker Nscale (JV)

Aker Nscale (JV) — Narvik

UTKAST FØR TILSVAR — tilsvarsrett ikke sendt ennå

Norway · Under development (JV closed; site development ongoing)

Status Under development (JV closed; site development ongoing)
Kapasitet (MW) 230 MW secured grid capacity; ~1.5 GW in development queue Kilder: www.aker.com · www.nscale.com
Kraftkilde (påstand) Norwegian hydropower grid (claim, UNVERIFIED — Narvik/Nordland is hydro-dominated but no direct operator power-source claim sourced this pass)
Publisert PUE UNVERIFIED — no PUE published; site still in development
Eierskap / jurisdiksjon 50/50 joint venture between Aker ASA (Norway) and Nscale (UK), closed 13 Oct 2025. CEO of the JV: Kristian Røkke (son of Aker's controlling owner Kjell Inge Røkke). HQ at Fornebu, operational teams in Narvik. Separate from Aker's 9.3% direct equity stake in Nscale itself (see Nscale Glomfjord entry). Kilder: www.aker.com · www.nscale.com
AI/GPU-relevans VERY HIGH — anchored by a five-year, multi-billion-dollar Microsoft compute offtake agreement and the 'Stargate Norway' project with OpenAI. Materially larger and more strategically significant than Glomfjord. Kilder: www.aker.com · www.nscale.com
Verifikasjonsnotater New entry added 23 Jul 2026 (previously out of scope/not tracked). Genuine Norwegian strategic capital (Aker, sitting industrialist's son as JV CEO) is a real sovereignty data point, but the JV is 50/50 — do not overstate as 'Norwegian-controlled.' Contacts: [email protected], [email protected]; Kristian Røkke likely most relevant addressee for Narvik/ownership questions specifically. Pre-review: right of reply not yet sent.
Felt merket UVERIFISERT kunne ikke bekreftes mot en offentlig kilde. Vi publiserer usikre data som usikre. Datafeltene vises på engelsk (kildespråket).